3 Operation
Step 1 (Fig. 1)
Wilt the rope head downward and pressing the hoist, push the relaxed handle. When hearing the sound click, pliers mouth has
been opened. Then you can bring the wire rope from the back hole to the hoist. After the rope is out, the rope can be pulled
to the length that you need and the push the relaxed handle back to clamp the rope tightly. When the forward handle or the
backward handle pulled, the wire rope will automatically go into or come out of the hoist. Thus, the machine is in the normal
state and it is ready to be used.
Step 2 : Anchor
Fixed axis is to be used to anchor the rope round the hoist. Connect the wire rope or the hanger with the fixed rope and tie
the other end to the load, masts, etc. There is a relaxation-proofing tunnel on the fixed axis. When the fixed axis is inserted the
hoist case, is must be turned twice to the second tunnel till it is clamped tightly (Fig. 2).
Then the operation can be done. Notice: The end of the wire rope must be on the upper of the fixed axis so as to make the
rope not block and move freely.
Step 3 : Operation
Hook the load of the hanger. Do as following:
1. Lift (forward) tension : pull the forward handle. (Fig. 3: A, B)
2. Lower (backward) : pull the backward handle. (Fig. 3: C, D)
3. Stop working : whenever lifting or lowering the load, is will stop working to make the load stay in any position when the
manual handle stops working.
4. Draw the rope out (Fig. 1) : Having finished the work, the pliers mouth will be opened as soon as the relaxing handle is
pushed and then the wire rope can be drawn out of the end of the hoist. Clean the dirt on the rope, wind it onto the reel
cross in good order to be ready to use next time. Finally, push back the relaxing handle in order not to let pliers mouth
open for long to keep the pretension spring working well later.
Rope reeving and rope receiving: Push the relaxed handle to front
direction by hand so as to insert it into the step formed on the top inner
wall of the inside.
A to lift a load (or pull a load forward): Pull the handle forward.
Fig. 1
Turn and push the fixed axis twice
and let it enter the second tunnel.
Fig. 3A