Page 12
ENGLISH
3.4
Installing the Cell
The cell must be installed horizontally with the
cord facing upwards to avoid buildup of flammable
gases which can result in FIRE OR EXPLOSION. In
Canada, the Jandy chlorine generating electrolytic
cell must be installed outdoors.
Standard Installation
The standard installation consists of plumbing the
housing unit of the TruClear directly into the pool
plumbing system, without the use of threaded unions.
1.
Determine the desired location for the cell as the
last piece of equipment before the return inlet to the
pool, on a pipe segment at least 16 inches long. The
cell must be mounted upright on pipe which runs
within ± 5º of level (parallel to the ground). The cell
cannot be mounted on a vertical, or sloping pipe.
NOTE The cell must be installed on a 16 Inch (40cm)
horizontal length of pipe after the heaters, pumps,
and filters, as the last piece of equipment in the
circulation plumbing system before the pool inlet
(see Figure 1).
2.
Make the appropriate cuts in the pipe where you
will be installing the cell. The gap between the cuts
should be 6 inches.
3.
Remove the cell from the housing and plumb the
housing into the pipe, making sure that the fl ow
indicator arrows on the housing match the fl ow
direction of the water. Pipes must be clean and dry
before gluing.
Jandy
TruClear
®
WARNING
|
Chlorine Generating System
™
NOTE If the flow direction of the water does not
match the arrows on the housing, the cell will
malfunction.
4.
Let the system dry per instructions provided by the
glue manufacturer.
5.
When the glue is dry, install the cell into the cell
housing. Secure the cell by engaging the lock ring
and ensure that the fl ow indication arrows on the
transparent lid correspond to the arrows on the cell
housing.
6.
Start the system and check for proper water fl ow.
To avoid property damage, serious injury or death, do not
operate the electrolytic cell without water circulation or if
cell housing is damaged or improperly assembled.
Retrofi tted Installation
The retrofi tted installation is a factory designed TruClear
with threaded unions built into the housing unit. This
method can be used to replace an existing chlorine
generator or as a new installation.
1.
Determine the desired location for the cell as the
last piece of equipment before the return inlet to the
pool, on a pipe segment at least 16 inches long. The
cell must be mounted upright on pipe which runs
within ± 5º of level (parallel to the ground). The cell
cannot be mounted on a vertical, or sloping pipe.
Installation & Operation Manual
WARNING