Assembly
It is typically installed in a junction box or a deep switch box (with at least 60 mm full
surface depth) in the centre behind the CentralControl CC51. Incoming and outgoing
lines must only be routed vertically so as not to come into contact with the fixing holes
on the CentralControl CC51. Wiring of the mains connection wires in the junction or
switch box must be done on the ground. The CC51 flush mounted power supply unit
must then be inserted in such a way that all mains connection wires are positioned
below the CC51 flush mounted power supply unit and are therefore covered. The
CentralControl CC51 connecting cable must be routed out of the junction or switch
box on the front side and mounted using appropriate strain relief. Wiring is carried out
according to the connecting diagram.
17 - en