Prepare The Site - Kohler K-710 Guide D'installation Et D'entretien

Masquer les pouces Voir aussi pour K-710:
Table des Matières

Publicité

1.

Prepare the Site

Drop-In Installations
Installations à encastrer par le dessus
Instalaciones de sobreponer
Provide a 1/16" (2 mm) gap between the bath rim
and the framing.
Fournir un espace de 1/16" (2 mm) entre le rebord
de la baignoire et la charpente.
Provea una separación de 1/16" (2 mm) entre el
borde de la bañera y la estructura de postes de
madera.
NOTICE: Measure your product for site preparation. Visit the product page at
www.kohler.com for more information.
Flooring
Provide adequate floor support.
NOTICE: To ensure a successful installation, it is critical that the bath be installed on
a level subfloor.
Verify the subfloor is level. Adjust for level, if necessary.
For freestanding installations, apply water-resistant sealant to the subfloor. This
will reduce the risk of water damage.
Framing – For Drop-In Installations
CAUTION: Risk of property damage. Do not support the bath by the rim. The
bath must be supported by the feet only.
NOTICE: Take into account the thickness of the finished wall materials when
constructing the framing. If these factors are not taken into account, the bath will not
fit in the installation area.
NOTICE: To ensure the bath does not rest on the rim, a 1/16" (2 mm) gap must exist
between the underside of the rim and the framing. When constructing the framing,
take into account the 1/16" (2 mm) gap and the thickness of the finished wall/deck
material. If these factors are not taken into account, the bath will not fit in the
installation area.
Construct the framing. Ensure a 1/16" (2 mm) gap will exist between the
underside of the rim and the framing.
1084217-2-B
4
Kohler Co.

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

K-711

Table des Matières