TC 12. Commissioning and Inspection

TC 12.1 COMMISSIONING
To be done
Component/parameters
Check for residual
§
§
Pipes
§
§
Valves
§
§
Probes
§
§
Nozzles
Check spray water quality
Current chemical and microbiological analysis of the spray water in accordance
with the specification
Unit for makeup of spray water
Unit installed and ready for operation
and online control
Check AFS
§
§
The Air fresh system is installed properly
§
§
The Air fresh system is operating properly
§
§
The Pump in technical room
Documentation
Documentation complete and handed over to the operator
Instruction
The operator is instructed
TC 12.2 INSPECTION
Action to be done and documented regularly, besides those listed in materials for the heat exchanger:
Position
Component/parameters
Frequency
1
Unit for makeup of spray water and
Yearly
online control
2
Spray water
Quarterly
3
Probes
Yearly
4
UV Lamp
Yearly
5
Spray nozzles
Monthly
6
Complete unit
Monthly
21
MT TC R AFS EN 03 2018
Action to be done by indication
Inspection of functioning and damages
Chemical and microbiological analysis
Inspection of functioning, residues and damages
Inspection of functioning, residues and damages
Check spray
Check for damage, leakage and residues
Technical Manual TC Instruction and technical data
MT TC R AFS EN 03 2018
22