PRE - START UP PROCEDURE:
Before operating your EcoSalt ensure the following items have been added to your pool:
• SALT - Load salt into the pool at a minimum rate of 40kg per 10,000 litres (0.4%).
Connect vacuum system and slowly vacuum until salt dispersal is complete. Place
vacuum head into deepest end of pool and allow vacuum to continue for a further 2 or 3
hours. Salt should now be completely disolved.
• CHLORINE - For a new pool installation that has not been chlorinated, add sufficient
Chlorine (liquid or granular) to achieve a reading of 3 ppm (with a suitable test kit), or run
the chlorinator system continuously for at least 24 hours or until a reading of 3 ppm is
reached.
• STABILISER - It is essential that pool stabiliser be added and maintained at the rate
of 30 - 50 mg/l (30 - 50 ppm) at all times. Do not exceed 80 ppm. If you are using an
ORP controller, the stabiliser level should not exceed 15ppm.
OPERATION OF ECOSALT SYSTEMS:
Cell Output is expressed as a percentage. Set the system control to the percentage
output required and the unit will automatically adjust the cell output to the set level. The
Unit is fitted with an electronic control and warning system. This regulates the output of
the Unit to the preset maximum and changes cell polarity as indicated by POLARITY
LEDs A & B. These LEDs will alternate over a number of hours or days depending on
how the unit is set to operate. The warning system consists of one Operation LED
which will glow Green to indicate normal operation or Red to indicate possible faults with
the Unit or damaging operating conditions.