IMEON INVERTER
8.2 Inverter maintenance and update procedures
To restart or decommission the inverter completely, please follow the steps below.
8.2.1 Shutdown the inverter
1- Switch all protective devices to OFF position in the following order.
PV switch
Battery switch
AC breakers
2- Wait for the LCD display of the inverter to shut down (maximum 30sec)
8.2.2 Uninstall the inverter
1- Unplug the PV, Batteries, AC GRID and AC BACKUP connectors
2- Disconnect the ground cable from the inverter
3- Disconnect the communication cables (Ethernet, CAN etc.)
4- Unscrew the 2 support screws fixing the inverter to the wall mounting plate
5- Remove the inverter from the wall mounting plate
Note: In order to supply power to consumers connected to the AC BACKUP output, it is possible
to connect the AC GRID and AC BACKUP connectors together.
8.2.3 Reinstall the inverter
1- Place the inverter on the wall mounting plate
2- Screw the 2 support screws fixing the inverter to the wall mounting plate
3- Connect the communication cables (Ethernet, CAN etc.)
4- Connect the ground cable of the inverter
5- Make sure that all protective devices (PV switch, battery switch and AC breakers) are in the
OFF position.
6- Plug the PV, Batteries, AC GRID and AC BACKUP connectors
8.2.4 Restart the inverter
1- Switch all protective devices to ON position in the following order.
AC breakers
Battery switch
PV switch