• Move the lift rails to about half height.
• Remove the lifting arm (remove the safety ring of
the lifting arm pin, pull out the lifting arm pin and
remove the lifting arm).
• Disconnect electrical supply lines to the lift from
mains power.
• Remove hydraulic lines above on the opposite
side and seal them off with blind stoppers.
• Only loosen cross beams on one side and fold
them under along with the hydraulic lines.
• Securely fix the beam to the columns.
• Suction off hydraulic oil.
• Loosen the anchor fastenings.
• Carefully transport the lift column using appropri-
ate auxiliary means (e.g. crane, forklift, etc) to the
new assembly location.
• Assemble the lift according to the procedure dur-
ing assembly and anchoring before first commis-
sioning.
Use new anchors. The old anchors are no longer
!
fit for purpose.
98
OPI-POWER LIFT HF 3S 3000-4000 - HYMAX HF 3S 3000-4000 -V1.1-DE-EN-FR-ES-IT

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Nussbaum hymax hf 3s 3000Nussbaum power lift hf 3s 3500Nussbaum hymax hf 3s 3500Nussbaum power lift hf 3s 4000Nussbaum hymax hf 3s 4000

Table des Matières