IMPORTANT: For proper installation and smooth operation, the valve must
be level and square to the finished wall.
• Install the valve so that the outside
surface of the finished wall will be
between the Max and Min markings
on the plaster guard.
• Make sure the valve is installed with
the small arrow pointing upward.
• The plaster guard should remain in
place until you are ready to install the
trim.
IF YOU ARE INSTALLING MODEL TS2A:
• Model TS2A is a single outlet valve.
Make the connection as shown to the
right.
IMPORTANT:
The left and top outlets are plugged for
the valve to operate correctly.
IF YOU ARE INSTALLING MODEL TS2D:
• Model TS2D is a dual outlet valve.
Make the connections as shown to the
right.
IMPORTANT:
The top outlet must be plugged for the
valve to operate correctly.
INSTALLATION PROCEDURE
4
Finished
Wall
Up Arrow
Plug
Up Arrow
Outlet 2
Max 95mm
(3.75")
Min 65mm
(2.50")
TS2A
Outlet
Inlet
TS2D
Outlet1
Inlet