Télécharger Imprimer la page

turbionaire SMART 16 eco Manuel D'instructions page 15

Masquer les pouces Voir aussi pour SMART 16 eco:

Publicité

All manuals and user guides at all-guides.com
contaminated. The hoses should be as short as possible to minimize
the quantity of the refrigerant contained therein.
-
The cylinders must be kept upright.
-
Ensure that the cooling system is grounded before filling the
system with refrigerant.
-
Label the system after filling it with refrigerant (if it is not
already labelled).
-
Do not overload the cooling system.
Before refilling the system, it must be tested with OFN. The system must be
checked for leakage when the filling procedure is completed but before the
unit is placed in service. After the filling procedure, perform a leakage detection
test.
16) Decommissioning
Before performing this procedure, it is essential that the technician is completely
familiar with the equipment and with all its components. It is recommended
that all refrigerants are safely recovered. Before performing this procedure, a
sample of oil and refrigerant is taken if an analysis is required before re-
using the regenerated refrigerant. It is essential that the power supply is
available before the procedure begins.
a.
Familiarize yourself with the equipment and with its operation.
b.
Insulate the system from the electrical point of view.
c.
Before proceeding, make sure that:
d.
Mechanical handling equipment is available if it is necessary for
the handling of coolant cylinders;
e.
All individual protection equipment are available and correctly used;
f.
the recovery process is permanently supervised by a qualified
person;
g.
The recovery equipment and cylinders are in accordance with
the appropriate standards.
h.
If possible, drain the cooling system.
i.
If aspiration is not possible, use a collector so that the refrigerant can
be removed from different parts of the system.
j.
Ensure that the cylinder is in upright position before recovery.
k.
Start the recovery machine and use it in accordance with the
instructions of the manufacturer.
l.
Do not fill the cylinders. (Must not exceed 80% of the quantity
of liquid).
m.
Do not exceed the maximum working pressure of the cylinder,
even temporarily.
n.
When the cylinders have been correctly loaded and the process
has been completed, make sure that the cylinders and the
equipment are quickly removed from the working area and that
all the insulation valves of the equipment are closed.
EN

Publicité

loading