1 - INSTALLATION AND COMMISSIONING
1.3 - Connecting ports
The connections to be performed on the equipment depend on the configuration chosen:
On the power supply card:
S
poser supply ports: "PWR" or "PWRA" and/or "PWRB",
On the subrack motherboard strip:
management ports : "COMM", "ETH" and/or "MNGT"
S
S
Remote indication, remote control and station alarm port : "LOOPS"
S
2Mbit/s G.703 synchronization port : "SYNC"
S
21x2Mbit/s G.703 traffic ports: "E1 INPUT" and "E1 OUTPUT".
Depending on the traffic modules used
S
optical STM-1 ports and order wire channels ports,
Ethernet port
S
21x2Mbit/s G.703 traffic ports.
S
Connection requirements :
Ö
For a right distribution of cords on either side of the subrack, the connections of slots A and
C, the 21 2Mbit/s accesses and synchronization access are oriented leftward. All other
connections are oriented leftward.
Ö
The run of cords must not hinder the extraction of a module; in particular, connecting
cables of the left subrack half is to be secured to the frame with enough backlash to
enable the ventilation module to be extracted during a maintenance operation.
1.3.1 - Connecting Power Supply
S
"PWRA" and/or "PWRB" ports, when the equipment is powered from one or two 48 V
sources, the power source(s) should be limited to 100 VA.
S
. "PWR" port when the equipment is powered from a mains voltage (230 V AC), via an
optional 110-240//48V 60W/ transformer.
Observe the following connection requirements :
Ö
"PWR" and "PWRA" and/or "PWRB" Power supply ports can be connected simultaneously.
Ö
The power cord or the 110-240//48V 60W/ transformer must not be connected to the primary
source prior to being connected to the equipment.
Ö
The 110-240//48V 60W/ transformer must be mounted far from any heat source, and no
traction must be exerted on its connecting wires.
Installation and User Guide - N56717020101
Page A1-4