Commissioning
6.1
Commissioning the product
1. Attach a label in the vicinity of the discharge line or to the safety valve with
the following text:
"For safety reasons, water must be able to escape via the discharge
line during heating. Do not shut off!"
2. Verify that all water connections are water-tight.
3. Flush the entire pipe system prior to commissioning the system.
6.2
Function test
1. Provide a suitable container to collect the discharged liquid.
2. Protect all persons from escaping liquid.
3. Open the product by turning the cap.
- Liquid escapes.
- After releasing the cap, no liquid may escape from the safety valve.
7
Operation
 Verify that liquid can escape via the discharge line of the safety valve dur-
ing heating up.
 Verify that the safety valve is not shut off.
1. If the safety valve has triggered, check the system before recommission-
ing the system.
2. Perform a function test of the safety valve (see chapter "Function test").
8
Maintenance
8.1
Maintenance intervals
When
Every 6 months
Commissioning
Activity
Perform a function test of the safety valve (see
chapter "Function test").