FLUSH Flange Carpet Installation – FLUSH (shown): Open Cover and turn four Jack Screws to raise Flush Flange with
Cover flush to surface of Carpet floor.
Figure F
Pour Depth
See Table
and refer
to Fig. 4.
Carpet Flooring
Floor Box
Pour Depth
Flush Flange With Cover
CFB10G55, xxCR
6.0"
610GTCVRxxC
ATTACHING THE COVER: 610GTCVRxx rectangular cover assembly shown
•
NOTICE: Use only electrical grade type RTV silicone sealant to insure scrub water tightness.
•
Apply bead of Silicone compound underneath of Flush Flange as shown depending on application Tile or Carpet.
•
Pull and Lift Cover upright at 90° as shown to access Jack Screws.
•
Attach cover assembly to top mounting plate using jack screws [7]. Fasten until flange is level and secure to floor.
•
To adjust cover assembly turn jack screws [7] counter clockwise to raise or clockwise to lower. Sequentially turn four jack screws as needed for proper
leveling of flange to floor. The jack screws have a 1 inch maximum adjustment.
Figure 5
Jack Screw (4x)
7
PD2527
(Page 6)
08/16
To attach
Flush
Apply Grout
Flange,
or
See Fig. 5.
Silicone
Carpet
compound.
Pull
Cover
Gasket
Apply silicone
sealant
Pre-assembled Locknut
Jack Screw (4x)
After Concrete Pour Box installation:
CAUTION: Temporary concrete covers are intended to keep
concrete residue from entering box during pour and are not
Cover
intended to support loads. Replace with permanent flange/
cover immediately after concrete has hardened or temporarily
reinstall concrete metal cover [4].
8. After concrete has hardened, remove temporary concrete
metal cover [4] and plastic cover [5]. Retain these temporary
covers.
9. Use wiring channel [7] for feed through. Wiring channel areas
given in Table 1. (Wiring channel must be removed for feed
through applications.)
Jack
10. Pull and dress wires.
Screws
11. Reinstall wiring channel. Align with notches [6]
12. Consult
electrical
instructions for wiring device installation.
13. Attach Flange with Cover (see Figure 5). For desired flange
styles see Figures A,B,C,D,E or F.
Ensure to set height of the top of the box (Figure 4) with plastic
cover [5] or without plastic cover (Figure 3) as indicated. See
Figures A, B, C, D, E, or F with tables for desired floor finish.
Figure 3
WITHOUT PLASTIC COVER
Pour concrete flush to Top Plate
Flush Flange
(shown)
Remove plastic cover
and tape all holes and seams
Applications:
Ceramic Tile (See Fig. A, Fig. B or Fig. C)
Laminate Flooring (See Fig. A, Fig. B or Fig. C
Carpet Flooring with Flat Flange (See Fig. E)
VCT with Flat Flange (1/8" Min. Thick. See Fig. B)
PD2527
(Page 3)
08/16
CFB10G55, CFB10G55CR
device
mounting
plate
installation
Figure 4
Temporary concrete
Pour concrete flush to Top Plate
4
metal cover
Applications:
Finished Concrete with Flush Flange (See Fig. D)
VCT with Flush Flange (See Fig. D)
Carpet Flooring with Flat Flange (See Fig. F)
Table 1
Catalog No.
Wiring Channel Areas
(1) 2.497 in² [1610.9 mm²]
WITH PLASTIC COVER
5
Additional ½"