12 - COMMISSIONING
After making the necessary electrical and hydraulic connections, carry out the unit commissioning, checking the following steps:
• Check the tightness of the electrical connections.
• Check the hydraulic connections (direction of inlet/outlet connections).
• Make sure the inside of the unit is clean and free from foreign bodies.
• Make sure the inside of the unit is clean and free from foreign bodies.
• Check the power supply voltage and heat protection rating in accordance with the currents for the various components.
• Check the siphon height.
• Vent the air out of the coils via the air bleed valves.
• Check the tightness of the circuits; retighten the valve if necessary.
• To configure the setpoints, please refer to the control manual. "CARRIER CCU Controller"
• Depending on the solution chosen, the air flow may be.
• adjusted based on the difference with the setpoint.
• constant.
(refer to the control manuals for the corresponding configurations)
• If a master-slave control system is used, make sure each unit is interconnected by a connection cable.
• Simulate a trip of the electrical components, controlled instruments and alarms.
• Check the current of each.
Standard components:
• Temperature alarm.
• Air flow alarm.
• Water leak alarm.
• Fan motor assembly.
Optional components:
• Temperature low limit alarm.
• Outer contact control.
• Electric heater.
• Humidifier.
• Hot water valve.
- Check the cleanliness of the humidifier supply water (option).
- After allowing the unit to run for a few hours, check the clogging level of the filter, especially in the case of an F7 filter.