Installation of failure monitoring kit,
Mounting, CDP
75/125/165
Technical data
8
Follow the below procedure to install the PCB in CDP 75, 125 or 165:
Step
1
Switch off the current to the dehumidifier
2
Remove the four screws to the central panel and remove it
3
Remove the four screws to the base panel and let it hang in the cables
4
Mount a spacer in each of the four holes at the bottom of the control panel.
Fix the spacer by means of a screw through the hole from the back of the
control panel (screws and spacers are included in the bag)
5
Place the monitoring PCB onto the four spacers so that the holes fit the spac-
ers. Fix the PCB by means of the screws in the bag
6
Mount the flat cable on the PCB in J1
7
Mount the other end of the flat cable in the socket on the main PCB in the up-
per left corner.
NB! On CDP 75 the flat cable is mounted on the small PCB just above the main
PCB!
8
Establish connection from terminal points 1, 2, 3 and 4 dependent on the
surveillance system to be used (to be done by the installer on the site).
NB: Relevant materials are not included
Maximum load is 50 V, 500 mA.
The relays' switch on / switch off functions are connected on terminal points 1 – 2 – 3 -
4.
continued
Action