5. INSTALLATION PROCEDURE
Warning: Keep module & charge point switched off
during installation!
Step 1: Prepare the cable between chargepoint and
Load Shedding module. The maximum length of the
cable between charge point and Load Shedding module
is 20 meters;
Step 2: Feed the UTP cable(s) through the rubber stop(s)
on the data cable inlet;
Step 3: Clamp a RJ12 connector straight to the cable
and then connect it to the P1 port, as indicated in the
'3.4.2 Overview Installing Accessories' section;
Step 4: Don't plug the power adapter in the power outlet
yet;
Step 5: Connect the power adapter to the Load
Shedding module. One of the two power adapter wires
has a broken white stripe. This wire is the power adapter
GND and should therefore be connected to the GND pin
(right) on the module. The other wire is the +5 Volts and
should be connected to the +5V pin (left) on the module.
The middle pin is not used;
Step 6: Connect the CT('s) to the Load Shedding
module;
Step 7: Install the Load Shedding module on the DIN Rail
in the fuse box;
Step 8: Apply the CT('s) to the grid connection(s). Make
sure to apply the CT(s) so that the total power usage of a
phase is measured;
Step 9: Plug the power adapter into a power outlet. The
PWR LED must light up;
Step 10: The CS LED will (after a few seconds) indicate a
measured current after the power is on;
Step 11: Plug in the RJ12 cable to the Load Shedding
module.
If both ends of the cable are properly connected to
the charge point & Load Shedding module and powered,
the P1 LED will indicate whether the connection is
correct.
INSTALLATIEHANDLEIDING – P29
INSTRUCTION MANUAL – P29 | P29
5.7 LOCAL CONFIGURATION (UTP)
Make sure both the charge point and laptop are
powered for at least 5 minutes.
Continue to Chapter 6 and follow instructions for local
configuration.
5.8 FINISHING UP (CLOSE
ENCLOSURE)
Step 1: Check and make sure that the rubber seal of the
casing is properly in place on the edge;
Step 2: Place the cover on the charge point;
Step 3: Hand-tighten the four M4 x 12mm bolts provided
around the socket so that the cover closes on the rubber
seal but the rubber seal does not deform;
Step 4: Hand-tighten the other two M4 x 12 mm bolts
provided in the bottom of the cover;
Step 5: Turn the socket lid clockwise in the cover and
hand-tighten the M4 x 16 mm bolt provided;
Step 6: Switch on power to the charge point;
Step 7: Wait until charge point is fully started up (+/-10
minutes, LED should be off)