Installation; Installing The Template Box; Mounting The Appliance; Pump Heads - Baxi MS THINK+ Instructions D'installation

Appareil pour la gestion d'un circuit mixte a encastrer
Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

2. INSTALLATION

The appliance must be installed inside the template box, supplied separately.
Ensure that the model of the template box is correct.

2.1 INSTALLING THE TEMPLATE BOX

The template box must be fitted into the wall in a niche created for the purpose and blocked with special rag bolts at the sides.
Make sure the installation allows easy access for maintenance. The door and the white frame must be removed and fitted only
at the end of the installation phase (check that the key for opening the door is supplied with the box). The frame can be depth-
adjusted by using the 4 butterfly nuts located in the side guides. In this way it is possible to rest the frame on the plaster and
remove it if the wall has to be painted. Install the system, starting from the position of the water inlets present on the lower and
upper bars of the template (recess in the box: 30 mm). We recommend installing the box under or close to the boiler. It is advisable
to fit shutoff cocks (G3/4") on each inlet (available as accessories) to allow maintenance work, if required, without having to drain
the entire heating system.

2.2 MOUNTING THE APPLIANCE

After completing all masonry work, fix the MS THINK+ appliance inside the template box and make the hydraulic connections (for
the key to the connections and the hydraulic diagram see SECTION A at the end of this manual). Before fixing the module, make
the holes in the back wall to insert the Ø 10mm fixtures (use the holes in the template box as a guide). Then secure the module
with the supplied screws.
M
Delivery from boiler
R
Return to boiler
MAT
High temperature delivery
450
90
135
A
AE
M
472
82,5
229
2AT ERP
Ø 36 mm
B
MC1 RC1 MC2
RC2
57,5
65
67,5
67,5
If version 1AT-2BT is installed, the rectangular head screws in the Box Kit must be replaced with those supplied with the
product.

3. PUMP HEADS

The cross-sections of the circuit must be calculated according to the normal calculation method, bearing in mind the flow-head
curve available at the plate indicated in SECTION C at the end of this manual.
Mbt1
Low temperature delivery 1st zone
Mbt2
Low temperature delivery 2nd zone
Rat
High temperature return
135
90
R
210
Ø 36 mm
209
1
136,5
MC1 RC1
67,5
67,5 57,5
57,5
65
Rbt1
Rbt2
AE
3AT ERP
Ø 36 mm
MC2 RC2
MC3 RC3
67,5
67,5
67,5
67,5 57,5
13
Low temperature return 1st zone
Low temperature return 2nd zone
Electric power supply inlet
CG_2638
7222520.03 (1-11/15)

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

1at-2bt1at-1bt

Table des Matières