General information
Automatic hydraulic bollard.
Available with a painted steel tube or lined with an electropolished
AISI 316 stainless steel jacket.
The acoustic buzzer, the heater for particularly cold climates and
a pressure switch that prevents the tube exiting if there are people
or objects above it are available as optional accessories.
The MAX.CP control unit enables the management of two SPARTA-
CUS bollards for the protection of particularly large entrances.
Description
Figure 1 shows the main parts of the automation:
1 Head with flashing LED
2 200 mm diameter cylinder
3 Well lid
4 Adjustable magnetic limit switch sensor
5 Stop buffers
6 Electrical connection junction box
7 Hydraulic power unit
8 Hydraulic cylinder
Dimensions
Figure 2 shows the main overall dimensions, foundation box included.
In the foundation box must be broken:
1 Hole for 50 mm corrugated sheath for the passage of connection
cables (ref. C)
Preparation of the excavation
Referring to Figure 3, prepare an excavation of 900x900 mm with a
depth of 1300 mm(version 200/800) or 1100mm(version 200/600).
Prepare a gravel bed of 290 mm, we recommend gravel with a grain
size of 8/20 for good drainage.
Make sure that the gravel is well compacted.
Pay attention to the dimensions and levelling of the foundation.
Drainage test
Before inserting the foundation box in the excavation, carry out
the test described below, which is INDISPENSABLE for assess-
ing the level of permeability of the soil and taking the most suitable
measures to ensure that water does not stagnate in the excava-
tion but is absorbed as quickly as possible.
Pour 40 litres of water into the excavation and wait 30 minutes.
If the water takes longer than 30 minutes to be absorbed, despite
the drainage system, it will be necessary to lay pipes to channel
the water into a tank and, if necessary, to pump it out using an
electric pump.
Foundation box assembly.
Assemble the CA.200 foundation box referring to Fig. 4.
Fasten the individual parts, using the self-tapping screws 4.8x9.5
supplied.
Alternatively, ∅ 4x10 mm rivets can be used, which are also supplied.
Open the ∅ 50 mm hole for the passage of the corrugated cable duct.
Only open the highlighted hole (F) which refers to the direction of
impact of the casing.
Then fasten the frame K to the casing.
12 SPARTACUS
Installation manual
Laying the foundation box
Proceed with the insertion of the foundation box (Fig. 6) inside the
excavation, checking that:
- the positioning dimension is correct
- the crate is perfectly horizontal (use a level)
- the expected direction of impact is correct.
Prepare the passage of the 50mm ∅ corrugated sheath for the
passage of the connection cable to the control unit.
Add another 100mm gravel.
The concrete must be appropriately compacted (regarding the level
of the cast, consider the possible thickness of the floor).
The concrete must be properly compacted, taking into account the
possible thickness of the pavement in the casting level.
Wait a few days for the concrete to set before installing the bollard
in the foundation box, protecting the box with a waterproof sheet
in the meantime.
Electrical connections.
With reference to figure 6, prepare the electrical connections using
2
a 16x1.5mm
Only use cables that are suitable for the type of use required by
the installation and that comply with current local regulations.
Block the cable with two ties.
Inside shunt box B, there is terminal board (Fig.7) for connection
of the ramp to the MAX.CP control unit.
For further information, refer to the instructions supplied with the
MAX.CP control unit.
Installation of the bollard.
As shown in figure 8, to allow the bollard to be inserted inside its
foundation box, it is necessary to provide an extra connecting
cable (ref. C) from the base of the bollard to the beginning of the
foundation box.
Use the two G eyebolts supplied to lift the bollard and install it inside
the foundation box, paying attention to the cable as it descends.
Figure 9 shows the insertion position of the bollard in the foundation
box in relation to the intended direction of impact.
Secure the bollard to the foundation box using the 8 M12x25 stain-
less steel screws, as shown in Figure 10.
Installation of two bollards
In the case of particularly large gates, it is possible to install two or
more bollards as shown in figure 11.
The MAX.CP control unit is able to pilot two SPARTACUS bollards.
Emergency manual release
If necessary, the bollard can be lowered manually to allow vehicles
to pass.
As indicated in Figure 12, unscrew the Allen screw highlighted with
a 10mm key, remove the screw and exert pressure downwards,
the ramp will start to lower.
The unlocking system does not require resetting.
multipolar cable for all models.