3. Battery Cabinet Installation
6. Connect an appropriate equipment grounding cable to the grounding lug located on the top of the battery cabinet.
7. Feed the positive and negative cables (and "N" center, if equipped) from the open external disconnect switch or the UPS
battery field wiring terminals through the conduit/cable bushing. Connect to the respective output terminals inside the
battery cabinet.

3.8 Final Electrical Check

Before closing any connecting circuit breaker or disconnect switch, complete these verification steps:
1. Verify the battery cabinet output voltage is correct.
2. If battery cabinets will be operated in parallel, verify that the individual system output voltages match within 2V DC.
3. Verify the voltage measured between either output terminal and the battery cabinet ground is zero.
4. If any of the above verification steps show an irregularity, determine and correct the cause before proceeding.
5. Reset the circuit breaker to the "On" position.

4. Mechanical Data

4.1 Physical Measurements

4.1.1 Dimensions for BP240V65, BP240V65-NIB, BP240V100, BP240V100-NIB
31.5 in.
(800 mm)
47.2 in.
(1200 mm)
10
35.4 in.
(900 mm)