Start up
Burner start up simultaneously involves
starting up the installation by the fitter
or his representative; only he can
guarantee compliance of the boiler
house with currently accepted practices
and the regulations in force.
The fitter must first have obtained a
"certificate of conformity" provided by
the certified authority or by the network
undertaker and have leak-tested and
drained the pipework upstream from
the shut-off valve.
Preliminary checks
· Check:
– voltage supply and compare it with
that prescribed
– polarity between phase and
neutral wire
– potential difference between earth
and neutral wire.
· Switch off electrical supply.
· Check there is no tension.
· Close the gas valve.
· Read the instructions provided by
the boiler manufacturer and that of
the heat controller.
· Check:
– that the type of gas and the
distribution pressure are
appropriate to the burner.
– that the combustion air supply to
the boiler-house and the exhaust
pipe for the products of
combustion are compatible with
burner and fuel capacity.
– that the flue functions correctly.
Leakage test
· Connect a pressure gauge to the
upstream pressure take-off 119
located on the valve assembly.
· Open the shut-off valve.
· Check the supply pressure.
· Use a purpose-designed foam to
check the external tightness of the
valve assembly connections.
No leaks should be observed.
· If necessary, drain the pipework
downstream from the shut-off valve.
· Reclose the drain valve and the
shut-off valve.
Air pressure switch F6
The air pressure switch is pre-set to
10 daPa. This setting enables the
burner to be started under any
circumstances. Screw V can be used to
make adjustments after having checked
flow-rate and combustion test.
6,5
NC 9
5
NC 4, NC 6
25
01/2005 - Art. Nr. 13 010 553B
Settings
Combustion head:
The burner is delivered set for natural
gases.
To have access to the firing head:
· Loosen the four screws 5 five turns.
· Work the board free and pull until
completely clear.
· Hang the board from the hanging
point 7.
· Loosen (clockwise) the locking nut
on the gas head.
· Loosen completely (counterclockwise)
the spherical head screw E.
· Remove the firing head.
· Check position of the ignition
electrode, on the stop against the
gas star, and check position of the
ionization probe (see diagram).
When propane gas is to be used, the
GP diffusor on the board must be fitted
to the turbulator (see Conversion).
· Reassemble the board, following the
disassembly sequence in reverse
order.
· When reassembling, check that the
O-ring J2 is present and correctly
positioned.
· Check for leaks after reassembly.
Combustion air:
Set the flap opening (103/B) from 0 to
18, according to the chart.
+ air = – CO
and vice-versa
2
with no CO production
Secondary air:
Dimension Y governs the secondary air
between the turbulator and the blast
tube. Setting occurs by turning the
screw 15 . Reading is by the vernier
graduated 0 to 35mm.
By increasing this value
(counter-clockwise):
CO
decreases and vice-versa
–
2
nominal output decreases and
–
vice-versa
start up is "harder" and vice-versa
–
Burner
Dimen
Power
sion
Y
Type
kW
mm
15
17
NC4
25
20
35
25
40
25
NC6
50
30
60
25
NC9
70
30
85
35
EN
Air flap
103 B
0 to 18
3.5
8
12
13
18
9
11
18
43