English
Filling and starting up your buffer
tank for the fi rst time
The fi rst fi lling and start-up must be performed by a properly qualifi ed person.
Before fi lling the buff er tank with water, the pipes and the tank must be rinsed
to remove any debris and impurities. Upon start-up, pressure test must
be performed and the sealing of joints must be checked. If the tank will be
used in a cooling system, make sure the water temperature is always above
freezing point. To prevent corrosion in the system, it is recommended to treat
the water properly.
Option:
Connecting the electric heating package
(for fl oor-standing version only)
The buff er tank may be upgraded with electric heating to the designated
connection G1 ½.
The electric heating must be installed by a qualifi ed person.
Maintenance
The exterior of the buff er tank should be cleaned with a soft cloth and mild
liquid detergents. Do not use detergents that contain abrasives. Regular
maintenance interventions include the inspection of the expansion vessel,
safety valves and other valves, although they are not part of the appliance.
WE RESERVE THE RIGHT TO MAKE CHANGES THAT DO NOT AFFECT THE FUNCTIONALITY OF THE APPLIANCE.
9
CTC VT 50 - 300