Getting Started; Connecting The Weighing Platform - Sartorius Signum Notice D'installation

Table des Matières

Publicité

Les langues disponibles
  • FR

Les langues disponibles

4

Getting Started

Connecting the Weighing Platform

Connection of an analog Sartorius MAPP or MAPS platform or of a commercially
available strain-gauge load cell is described in the following.
!
The load cell should be connected only by a trained and authorized Sartorius technician.
Any installation work that does not conform to the instructions in this manual will result
in forfeiture of all claims under the manufacturer's warranty.
!
Disconnect the equipment from power (unplug from the wall socket) before beginning
any installation work.
§ Set up the weighing platform (see the operating instructions for the weighing platform)
§ Lay the cable for connecting the weighing platform to the display and control unit
§ Open the Signum display and control unit:
remove the four cap nuts from the front panel and remove the panel.
§ Connect cable from the weighing platform to the display and control unit
Note:
The cable gland is installed at the factory. Please use extreme caution when performing
any work on the equipment that affects this cable gland.
Use a torque wrench and tighten the cable gland to 5 Nm.
§ Prepare and install the cable as follows.
– Guide the cable through the cable gland.
– Close and tighten the cable gland in accordance with the applicable regulations.
– Remove the casing from a section of the cable end (see illustration). The shield (1) must
have contact with the clamps (2).
– Expose approximately 15 cm (4 inches) of the wires (3) for connection to the terminals.
– Guide the cable through the cable gland.
– It is important to make sure that the shield is in contact with the clamps, because the
cable is grounded by the shield.
§ Install the weighing platform cable as follows:
– Remove the casing from a section of the cable end. Expose approximately 5 cm (2 inches)
of the isolated wires for installation.
– Remove the casing from approximately 1 cm (1/2 inch) of the wires and attach ferrules to
the wire ends.
– Fit the ferrite ring over all wires.

Publicité

Table des Matières
loading

Table des Matières