30 | SBM 855 | Commissioning
4.

Commissioning

4.1

Unpacking

1. Remove the steel bands and fasteners.
2. Carefully lift off the packaging.
3. Remove the wheel guard, accessories and packaging
material from the packaging unit.
i
Check that the SBM 855 and the accessories are in
proper working order and that there are no visible
signs of component damage. In case of doubt, do
not start up the unit and consult customer service.
i
Remove the accessories and packaging material from
the packaging unit.
4.2

Set-up

1. Slacken off the bolts with which the SBM 855 is
attached to the pallet.
WARNING – Defective or incorrectly at-
tached lifting straps!
Risk of injury due to SBM 855 falling down.
Check lifting straps for physical damage
before attaching.
Tighten lifting straps uniformly.
Lift SBM 855 carefully.
2. Attach lifting straps of equal length and with an ade-
quate loadbearing capacity (at least 100 kg)
as shown.
|
656 229
2010-11-22
3. Use a crane to lift the SBM 855. Set up the unit in
the intended area, paying attention to the specified
minimum distances.
i
For safe and ergonomical operation, it is advisable
to set up the SBM 855 at a distance of 500 mm from
the nearest wall.
4. Fasten the SBM 855 to the floor at a minimum of 3
points.
4.3
Fixing the control panel in position
and connection
1. Lower the control panel column completely into
the socket provided behind the weight pockets.
2. Turn the control panel to the desired position and fix
the column in position with the bolt.
3. Connect the interface cord (Item 1) to
the interface connection on the back of the
SBM 855.
1