2.Safety Instructions
2.1 Important Safety Instructions
The AU-1P300/350/400/6002G microinverter is designed and tested according to international safety
require ments. However , certain safety precautions must be taken when installing and operating this
inverter. The installer must read and follow all instructions, cautions and warnings in this installation
manual.
All operations including transportation, installation, start-up and maintenance must be carried outby
qualifed, trained personnel.
Check the product before installation to make sure there is no damage caused during transportation
because such damage can compromise the insulation integrity and safety clearances.
Choose installation location carefully and adhere to specifed cooling requirements. Unauthorized
removalof necessary protections, improper use, incorrect installation and operation may cause damage
to the equipment or incur serious safety and shock hazards.
You should get necessary approvals from local power operator before connecting the microinverter to the
power grid. This connection must be made only by qualifed technical personnel. It is the responsibility of
the installer to provide external disconnect switches and Over Current Protection Devices (OCPD).
Each input of the inverter is connected to one PV module. Do not connect batteries or other sources of
power supply. The inverter can be used only if all the technical parameters are observed and applied.
Do not install the equipment in flammable, explosive, corrosive, extremely hot/cold, and humid environm
-ent. Do not use the equipment when safety devices in these environments are not working.
Personal protective equipment such as gloves and goggles must be used during installation.
Inform the manufacturer about non-standard installation conditions.
Do not use the equipment if any operating anomalies are found.
All repairs must be done with qualifed spare parts which must be installed in accordance with their inten
ded use and by a licensed contractor.
Liabilities arising from components that are not produced by Austa are on the part of their respective
manufacturers.
Whenever the inverter has been disconnected from the public grid, please be extremely careful as some
components can retain charge sufcient to create a shock hazard. Before touching any part of the inverter,
please ensure the surface and the whole equipment are within the limit of safe temperature and voltage
potential.
Austa is not liable for any damage caused by incorrect or improper operation.
Electrical installation and maintenance shall be conducted by licensed electrician and shall comply with
local wiring rules