Equipment Connections

Check that the indications on the name plate located on the back of the UPS correspond to the AC-power source and the
true electrical consumption of the total load
Evolution S 2500 / S 3000
a
1.
Input cable power source.
2.
Connect the loads to the UPS. It is preferable to connect the priority loads to the four outlets marked (7) or (9) and the
nonpriority loads to the programmable outlet marked (8).
To program shutdown of outlets (8) during operation on battery power and thus optimize the available backup time.
Fit the connection securing system (rack model only).
*Note: Input cord
NEMA 5-15P for S1250
NEMA 5-20P for S1750/2000
2.6

Connection with a FlexPDU (Power Distribution Unit) Module (optional)

Evolution S 2500 / S 3000
FlexPDU
45
2 — 4
All manuals and user guides at all-guides.com
46
48
Installation
Evolution S 1250 / S 1750 / 2000*
1. Evolution S 2500 / S 3000: Connect the UPS input
socket (10) to the AC-power source using the cable
(31) supplied.
Evolution S 1250 / S 1750 / 2000: Use the power
cable of the protected equipment.
2. Evolution S 2500 / S 3000: Connect the input socket
on the FlexPDU module (48) to the UPS outlet (9).
Evolution S 1250 / S 1750 / 2000: Connect the input
socket on the FlexPDU module (48) to one of the
outlets (9).
The cable and the connectors are marked in red.
3. Connect the equipment to the outlets (45) and (46) on
the FlexPDU module. These outlets differ, depending
on the version of the FlexPDU module.
4. Fit the connection securing system that prevents the
plugs from being pulled out accidentally.