Before the power is connected to the charging station, you must first call Ecotap® B.V.
on +31 (0)411 745 020 (Mo – Fr 09:00 to 16:00) so that we can activate its software (this
requires the unique charging station number).
19. OPERATING / INSTALLATION MANUAL
19.1 Open the door
The door is opened in the following way.
Use a flat-head screwdriver to open the cover plate from the cylinder lock by turning it half
a rotation.
Insert the key supplied into the right-hand lock and turn it clockwise until the handle is
released. Turn the handle to the right until both the top and bottom of the door are free.
Carry out these steps in reverse to close and lock the door.
19.2 Mounting on the foundation
To fit the foundation, a hole must be dug of roughly L 900 mm x D 450 mm x H 450 mm.
The bottom of the hole must be stable and levelled.
Place the foundation base level in the hole. The upper surface of the base must be flush with
the upper surface of the grade / paving. The foundation must then be reinforced by adding
at least two 20 kg bags of fast-setting concrete in the corners of the foundation.
After the fast-setting concrete has cured, the charging station can be mounted on its
foundation using the nuts and bolts provided (nuts to the top).
The hole in the foundation and the charging station must be lined up. See drawing of the
front of the foundation base. Take account of the connection face of the charging station in
relation to walls, hedges, etc.
Also keep in mind that there is sufficient space for the operation of the charging station. For
this we advise to keep at least 1 meter of free space around the charging station.