1.) DO NOT SHUT OFF BY DISCONNECTING SUPPLY CORD. THE HEAT EXCHANGER SHOULD BE
PROPERLY COOLED BEFORE POWER SHUTDOWN.
2.) ALWAYS MAINTAIN ADEQUATE FUEL SUPPLY.
3.) IF GAS BURNER IS INSTALLED HEATER IS FOR USE WITH PROPANE OR NATURAL GAS ONLY. SEE
APPROVAL LABEL.
4.) DO NOT PLUG ANYTHING OTHER THAN THE THERMOSTAT INTO THE "REMOTE STAT" PLUG.
5.) FOLLOW ELECTRICAL REQUIREMENTS SHOWN ON RATING PLATE AND/OR ELECTRICAL
REQUIREMENTS SECTION OF THIS MANUAL.
6.) IN OIL OPERATION DO NOT START THE HEATER WHEN EXCESS OIL HAS ACCUMULATED IN
CHAMBER.
7.) IN OIL OPERATION DO NOT FILL TANK WHILE UNIT IS OPERATING.
8.) IN NO CASE SHOULD POWER CABLES BE SMALLER THAN WHAT IS STIPULATED ON NAMEPLATE
AND INSTRUCTION MANUAL.
9.) IN OIL OPERATION DO NOT USE GASOLINE, CRANKCASE OIL OR HEAVIER THAN NO. 2 FURNACE
OIL.
10.) DO NOT START THE HEATER WHEN THE CHAMBER IS HOT
11.) DO NOT FILL THE TANK WHILE THE UNIT IS OPERATING
12.) DO NOT TAMPER WITH THE UNIT. HAVE A COMPETENT SERVICE-MAN MAKE ANY ADJUSTMENTS
13.) MAX OUTLET TEMPERATURE (U.S./CA) 250F/290F
14.) AT INSTALLATION ELEVATIONS ABOVE 2000 FT (610m), THE APPLIANCE SHALL BE DERATED 4
PERCENT FOR EACH 1000 FT (305m) OF ELEVATION ABOVE SEE LEVEL
15.) SHOULD OVERHEATING OCCUR, OR THE GAS SUPPLY CONTROL SYSTEM FAIL TO SHUT OFF THE
FLOW OF GAS, SHUT OFF THE MANUAL GAS VALVE TO THE UTILITY HEATER BEFORE SHUTTING
OFF THE ELECTRICAL SUPPLY.
16.) DO NOT USE THIS UTILITY HEATER IF ANY PART HAS BEEN UNDER WATER. IMMEDIATELY CALL A
QUALIFIED SERVICE TECHNICIAN TO INSPECT THE HEATER AND REPLACE ANY GAS CONTROL
WHICH HAS BEEN UNDER WATER.
ELECTRICAL REQUIREMENTS: 45 AMPS
INSTALLATION INSTRUCTIONS
1.) The recommendations of local authorities having jurisdiction must be followed. For
recommended installation practices refer to C.S.A. standard B139. (CANADA)
2.) When firing the unit in an enclosed area allow 1 square inch per thousand BTU's (refer to
C.S.A. B139) to allow the free entry of the air required for operation.
3.) For electrical supply:
Power Supply Installation
Single phase operation use L1 (RED) and L2 (BLACK) plus green for ground.
Three phase operation use L1 (RED), L2 (BLACK) and L3 (WHITE) plus green for ground.
4.) Do not operate the unit in partly ventilated areas without a flue pipe or in close proximity to
combustible surfaces or materials.
Tel: (905) 793-2525 | Fax: (905) 793-8768 | www.campoequipment.com
208V-240V SUPPLY WITH GROUND.
NOTE: Installation clearances are as follows:
TOP
SIDES
BURNER END
DISCHARGE END
CAMPO EQUIPMENT CO. LTD. (ECOBLAZE)
6 Carson Court, Brampton, ON, CANADA, L6T 4P8
2 inches
6 inches
2 feet
10 feet