I) QUICK START GUIDE
Once you have run the wiring and bridged, if necessary (LD5 LD6, and LD2 should always be switched on), perform the procedure below
in order to operate the gate:
1. Make sure the operator is connected on the Terminal Board J3 to the terminals 4-5-6 with its capacitor;
2. Connect the control unit to the mains;
3. Store at least 1 remote control (page 30). Attention: If the STOP button is not installed, bridge the terminals 10 and 12 on the Terminal
Board J4, otherwise no remotes can be inserted.
4. Check correct polarity of the connected motor: manually release the operator and position the gate halfway. Lock the operator. Give the
start command with the remote control: the first command after a power outage is always an opening. In case of closure, reverse
the motor terminals connection 4-5 on J3 terminal board;
5. Place the magnetic switches on the rack, according to the table below:
6. If the gate does not run, check the connection of safety devices, capacitor and possibly Bridge all contacts NC (normally closed,
LD5 LD6, and LD2 should always be switched on), and try again.
7. PROGRAMMING
Unlock the operator and place the gate in closing. Lock the operator.
Refer to the instructions page 30 of this manual
8. Set up the logic (step-by-step, automatic, condominium) and pause time as at page 31 of this manual, thrust with RV1 (slow-down speed
is set with RV1 but only during programming) and other customizations.
QUICK STEPS TO OPERATIONALIZE INSTALLATION
34
POSITION
LED STATE
OF THE GATE
LD3
LD4
Opened
ON
Closed
off
ON
Midway
ON
ON
off