Assembling Instructions for Specialist Staff Only
4
Optional door switch
Mount the optional door switch according to the as-
sembling instructions attached to the door switch, or
in accordance with the specifications of the cabin ma-
nufacturer.
5
Tests
Tests have to be conducted by an authorized electrical
engineer.
WARNING - Danger of Electric Shock:
The following tests have to be conducted with
supply voltage turned on.
1. Test contact to protective-conductor terminal.
2. Testing the safety shutdown of the stove sensor /
fuse with line:
-
The lines have to be disconnected at the stove sen-
sor to include the stove sensor lines in the test.
-
When disconnecting the white or red stove sensor
lead and when the white lead shorts out, the heating
system has to shut down by itself (red signal lamp
flashes).
3. Test the phase interconnection for the sauna ope-
ration L1, L2, L3 to U,V,W.
4. Test the phase interconnection for the steam
generator's operation L1, L2, L3 to U