Installation Requirements; Metal Ductwork Installation - activTek INDUCT 2000 Guide D'utilisation

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

INSTALLATION REQUIREMENTS

Installation Requirements
1. Unit should be installed after the air handler in the
HVAC system.
2. The ductwork around the installation area should be clean
and dry to ensure proper adhesion of the gasket materials
and any tape used.
3. When installing near a furnace or heating coils, run the
heating system through three (3) full heating cycles to
ensure the temperature of the INDUCT unit does not
exceed 200˚F.
4. An approximate 3.5" (8.89 cm) opening will need to be cut into the existing
ductwork to install the unit properly.
Electrical Requirements for 120 volt installation only
• To use a 120 volt plug, be sure to locate the unit within 6 ft. of a standard 120 volt grounded
outlet. Use of an extension cord is not recommended due to safety considerations.
• Install a US "B" UL approved plug onto the blunt cord.
Hardwiring Requirements (All units)
• Permanent wiring of the unit into your HVAC system must be done
by a licensed HVAC installer or electrical contractor only.
This unit is equipped with a universal ballast that operates at nominal voltages
between 100 and 277 VAC, 50/60 Hz.
For 120V domestic units: Black = L1, White = Neutral, Green = Ground
For commercial units: Black = L1, White = L2, Green = Ground
For International Units: Brown = L1, Blue = L2, Green w/yellow stripe = Ground

METAL DUCTWORK INSTALLATION

1
1. Locate suitable area
of duct for installation.
3
3. Mark location for 3.5" opening using either the
mounting plate or included template.
4
2
2. Cut away insulation to expose metal duct (if
needed).
4
4. Cut hole in duct using 3.5" hole saw.
Min. 8" x 8"
Air
Handler
Max. 6 ft.

Publicité

Chapitres

Table des Matières
loading

Ce manuel est également adapté pour:

Induct 750

Table des Matières