Finishing initial commissioning
8.9
Switching on the DC supply
Set the DC circuit breaker on the inverter to position I (Fig. 12).
After testing via the internal MSD (approx. 2 minutes), the power fed into the grid can be shown
on the display (assuming that sunlight is present).
Fig. 12: Set the DC circuit breaker to position I.
744.378 | 12.13
1. Press ESC to jump stepwise backwards and correct set-
tings or
Press and hold SET for a longer period of time to finish
initial commissioning.
2. If SET was pressed for a longer time then the inverter
restarts anew and synchronises itself with the grid.
EN
65