① Confirm that grid-tied operation has been manually stopped.
② Press the [RUN/STOP] button on the Remote Controller to start grid-tied operation.
The status lamp lights a green color and "GRID-TIED MODE" will be displayed.
③ Confirm the storage battery charge on the Remote Controller.
The value should be around 1.4kW charging.
④ Press the measurement unit switching button on the Hybrid Solar Inverter sensor display to switch the measurement
unit to "kW" .
⑤ Confirm that the measured value on the sensor display is greater than the storage battery charge on the Remote
Controller.
Value should be around 1.6kW.
⑥ If the displayed value is different, reattach the reverse power flow CT as explained in the table on the next page.
⑦ Press and hold the [RUN/STOP] button for 5 seconds or more to stop the grid-tied operation.
"MANUAL GRID STOP" will be displayed and the status lamp will turn off.
Measurement Units
Sensor CH
Sensor M
Measured Value
Sensor Channel Selector Button
(Not used)
Setting Button
(Not used)
Hybrid Solar Inverter Sensor Display
Measurement Unit Selector Button
35