5.
Check the rivets
Check that the rivets are held behind the smaller hole of the
support beam keyholes. Repeat steps 4 and 5 for each tie
channel support.
7.
Add wire shelves
P1
P3
Place the wire shelf (P1) on top of the tie channel supports (P3)
for each shelf.
9.
Move shelving
Two or more racks of the same height and depth can be
connected by sharing the same (P4) welded-end frame
between them.
NOTE: Ensure there are at least two shelves per rack between
each set of (P4) welded-end frames.
A
P3
B
Smaller
hole
C
P2
P4
6.
Check all beams and tie channels
P3
Verify that all support beams (P2) and tie channel supports
(P3) are properly assembled and firmly seated into the top
and bottom post slots.
8.
Move shelving
Using two or more people, move the rack shelving to its final
location.
P2