IX. INSTALLING THE CEILING ASSEMBLY (9600 SERIES)
Make sure that you have properly matched the roof top heat
pump and interior ceiling assembly. The following step-by-
step instructions must be performed in the following sequence
to insure proper installation.
A.
Remove ceiling assembly from carton, separate
individual items and remove the two grilles and
filters from the ceiling shroud.
B.
Fold and break off the 3 tabs around the inner
opening of the duct collar then fasten the duct collar
to the heat pump basepan with 3 provided screws
(See Figure 12).
C.
Raise the ceiling assembly chute and insert the
supply wiring through the cable clamp and into
the wiring box so that 4-6" of supply conductor
is inside the box. Secure the cable clamp over the
supply wire sheath so that no movement is possible
(See Figure 10).
D.
Connect the supply power black conductor to the
black pigtail wire, the white conductor to the white
pigtail wire and the supply ground conductor to the
green pigtail wire found in the wiring box using the
3 provided wire nuts. Using a U.L. approved
electrical tape, secure the wire nuts to wires in a
workmanlike manner (See Figure 11).
E.
Press supply conductors and wire nuts into wiring
box and making sure no wires are pinched, secure the
wire box cover with 2 provided screws (See Figure
11).
F.
Plug the heat pump electrical conduit into the 9
position receptacle as shown in Figure 10.
G.
If the optional heater accessory package is being
installed, remove the cover from the 2 position
FIGURE 10
receptacle and plug the heater cord into
receptacle as shown in Figure 10.
H.
Raise the ceiling assembly chute to the unit mounting
frame and secure the chute with 4 provided screws
(See Figure 12).
TIE ALL WIRING TO INSURE NO CONTACT
I.
WITH ANY SHARP EDGES OR WITH
OPTIONAL HEATER IS POSSIBLE. KEEP
IN MIND THAT HIGH VELOCITY AIR WILL
BE ENCOUNTERED IN THIS AREA.
J.
Pull the fabric duct material through the ceiling
chute discharge opening. Peel the release liner
from the adhesive strip around the opening.
Press the fabric duct material firmly in place
around opening. Cut off excess fabric on inside
of ceiling chute with a box knife taking care not
to tear the fabric beyond the adhesive strip.
K.
Raise the ceiling shroud and while insuring it
meshes with the chute, secure to mounting frame
with 4 provided screws (See Figure 12).
L.
Install the control knobs over the switch and
thermostat shafts. The thermostat (temperature)
control knob installs nearest the "Coleman-Mach"
logo.
M.
Re-install the filters and grilles into the ceiling
assembly shroud.
N.
Turn the selector switch to OFF position.
O.
Turn ON the power supply to the roof top heat
pump.
FIGURE 11
10