Use the installation guidelines as a reference only.
4.2 GENERAL DUCT WORK INSTALLATION
for more information.
•
•
•
•
•
Install dry air out duct/channel at a high level.
•
•
•
•
•
•
4.3 HUMIDISTAT/ELECTRONIC CONTROLLER INSTALLATION
Install the humidistat/electronic controller away from the dry air out path to avoid false readings.
4.4 CONDENSATE
from the drip pan.
The maximum hose length is limited to 20 meter and the maximum head is limited to 2 meter from the drip pan. Perform regular maintenance on the hose as well on the
level switch to ensure fault-free operation.
Caution!
4.5 ELECTRICAL CONNECTION
Electrical components should be connected to the supply according to the local regulations and requirements.
4.5.1 POWER SUPPLY
The single-phase cable is to be directly connected to the power grid with earthing capability.
See electrical diagram for a electrical voltage and operation frequency.