1. Turn OFF and lock out the power supplying the Safety
Switch.
2. Turn the Safety Switch OFF.
3. Remove Fuses.
4. Remove all load side conductors.
30 / 60 / 100 AMP LOAD BASE
©
2000 Siemens Energy & Automation, Inc.
Hazardous voltage.
Will cause death or serious
injury.
Turn off and lock out all power
supplying thisSafety Switch be-
fore installing kit.
Replace the covers and shields
before restoring power to
switch.
MOUNTING
SCREW
Fig. 1
Replacement Load Base Kit
Item:
Catalog Number HBB21, HBB22, HBB62,
HBB63, HBB612M, HBB64 & HBB623
60-200 Amp General Duty &
For use with:
30-200 Amp Heavy Duty Fused VBII
Safety Switches
1
2
Page
of
500200A01
Pc. No.
5. Remove the two mounting screws and Load Base.
See Fig. 1.
6. Position replacement Load Base at appropriate fuse
position. See Figs. 1 and 2.
7. Install the two thread-rolling screws supplied with kit
and torque to 29 lb-ins.
8. Install Load side conductors.
9. Install Fuses.
10. Close cover before supplying power to switch.