Section 4 − Installation; Location; Installation (Section 3-2 And Figure 4-1) - Miller Swingpak Manuel Du Propriétaire

Table des Matières

Publicité

!
Disconnect equipment input power conductors from deengergized supply line.

4-1. Location

When installing this unit, be sure to allow room for the boom to swing horizontally in the desired arc, and to pivot upward to the desired angle. The
location should allow room to remove panels of associated equipment for installation, inspection, maintenance, and repair procedures. Consider the
input power requirements as well as coolant (water) needs of optional equipment when choosing a location.
The service life and efficiency of this unit and associated equipment will be reduced if they are subjected to high levels of dust, dirt, moisture, corrosive
vapors, and extreme heat.
Mounting holes are provided in the Swingpak base for installing equipment.
4-2. Installation (Section 3-2 And Figure 5-1)
!
Overturning base can result in serious injury and equipment damage. Mount the welding power source on Swingpak base before
mounting Swingarc wire feeder into Swingarc support base. Do not install or operate on an incline. Do not lift the Swingpak base
with a forklift from the sides unless the lift forks extend far enough under the base to ensure against tipping.
!
Use bolts and fasteners of adequate capacity to assemble and install unit.
.
Refer to Section 3-2 and Figure 5-1 during assembly as necessary.
Remove hardware kit from underneath Swingpak base and proceed as follows:
1.
Secure the Swingpak base to the floor using 1/2 in. grade 5 (minimum) capscrews (see Section 3-2 for floor-mounting hole locations).
2.
Install boom support base onto Swingpak base using supplied 1/2-13 x 1-1/2 in. cap screws (Item 1, Figure 5-1) and associated hardware (see
Section 3-2 for mounting location).
3.
Locate appropriate mounting holes on Swingpak base for welding power source, and install power source onto Swingpak base using 3/8-16 x
1-1/4 in. cap screws.
4.
Install boom into boom support base following procedure outlined in appropriate Owner's Manual.
5.
If applicable, install coolant system mounting brackets onto Swingpak base using 1/4-20 x 1 in. cap screws.
.
If cooling system has mounting holes in base, do not install mounting brackets onto Swingpak base. Instead, install coolant system directly onto
Swingpak base.
!
Be sure input power is disconnected and welding power source is shut down before making connections to disconnect switch.
OM-1102 Page 10
SECTION 4 − INSTALLATION

Publicité

Table des Matières
loading