installation
electrical connection
Special connections:
1 phase connection (1 1N a.c. 230 V / 50 Hz):
The voltage between live and neutral is 230 V a.c.
Install connecting bridges between connection points 1-2 and
4-5. Your group must be protected by a fuse of at least 32 A.
The connecting power cable must have a minimum core
cross section of 6 mm
2
.
right zones
left zones
2 lives with 1 neutral connection (2 1N a.c. 400 V /
50 Hz):
The voltage between the phases and the neutral is 230 V a.c.
Between the lives there is a voltage of 400 V. If there is not a
voltage of 400 V between the lives, two wires have been
taken from the same live in the meter cupboard and the hob
must be connected with two neutral wires, as indicated
above under 2 lives with 2 neutrals. Install a connecting
bridge between the connection points 4-5. Your groups must
be fused with at least 16 A (2x). The connecting power cable
must have a minimum core cross section of 2,5 mm
2
.
right zones
left zones
GB 31