Purging The Piping And The Indoor Unit
Except for the outdoor unit which is pre-charged with
refrigerant, the indoor unit and the refrigerant
connection pipes must be air-purged because the air
containing moisture that remains in the refrigerant cycle may
cause malfunction of the compressor.
Remove the caps from the valve and the service port.
Connect the center of the charging gauge to the vacuum
pump.
Connect the charging gauge to the service port of the
3-way valve.
Start the vacuum pump. Evacuate for approximately 30
minutes. The evacuation time varies with different
vacuum pump capacity. Confirm that the charging gauge
needle has moved towards -76mmHg (0~76mmHg).
Caution
Wait for 15~20 minutes to check whether the gauge
reads a constant vacuum level. If gauge raeding
indicates higher level again, it means the presence of
water in the pipe, or leakages. In this case, remove
the water or check the leakages. After rectification,
repeat the above steps until a stable vacuum level.
Close the valve of the changing gauge and stop the
vacuum pump.
On the outdoor unit, open the gas valve (3 way) and
liquid valve (2 way) (in anti-clockwisw direction)
with 4mm key for hexagon sacked screw.
Additional Charge
The refrigerant is pre-charged in the outdoor unit. If the
piping length is less than 7.62m, then additional charge af-
ter vacuuming is not necessary. If the piping length is more
than 7.62m, then use the additional charge valve as indi-
cated in the table below.
Additional Charge In Gram (for R22 model only)
Model
10 m
WMS 10 F
35.7
WMS 15 F
35.7
WMS 20 C
35.7
WMS 10 FR
59.5
WMS 15 FR
59.5
WMS 20 CR
59.5
R407C must be charged as liquid. Usually R407C cylinder is equipped with a dip-pipe for liquid withdrawal.
If there is no dip-pipe, the cylinder should be inverted so as to withdraw liquid R407C from the valve.
Do not top-up when servicing leak, as this will reduce the unit performance. Vacuum the unit thoroughly and
then charge the unit with fresh R407C according to the amount recommended in the specification.
All manuals and user guides at all-guides.com
VACUUMING AND CHARGING
Charge Operation
This operation must be done by using a gas cylinder and a
precise weighing machine obligatorily. The additional
charge is topped-up into the outdoor unit using the suc-
tion valve via the service port.
12 m
15 m
65.7
65.7
65.7
110.7
109.5
109.5
109.5
184.5
! Caution
1-8
Allen key
Flare nut
Service Port
Outdoor unit 3 ways valve
Remove the service port cap.
Connect the low pressure side of the charging gauge to
the suction service port center of the cylinder tank and
close the high pressure side of the gauge. Purge the air
from the service hose.
Start the air conditioner unit.
Open the gas cylinder and low pressure charging valve.
When the required refrigerant quantity is pumped into the
unit, close the low pressure side and the gas cylinder valve.
Disconnect the service hose from service port. Put back
the service port cap.