Commissioning

8.1 General Information

To ensure that start-up is performed correctly, it should only be
carried out by an after-sales service technician authorised by the
manufacturer. This may be a condition for extending the guaran-
tee (see Warranty).

8.2 Preparation

The following items need to be checked prior to start-up:
The heat pump must be fully connected, as described in
Chapter 7.
The heat source system and the heating circuit must have
been filled and checked.
The dirt trap must be inserted in the brine inlet of the heat
pump.
All valves that could impair proper flow in the brine and heat-
ing circuits must be open.
The heat pump controller must be adapted to the heating
system in accordance with the controller's operating instruc-
tions.
E-6

8.3 Start-up Procedure

The heat pump is started up via the heat pump controller.
ATTENTION!
The heat pump must be started up in accordance with the installation and
operating instructions of the heat pump controller.
If an overflow valve is fitted to assure the minimum heating water
flow rate, the valve must be set in accordance with the require-
ments of the respective heating system. Incorrect adjustment
can lead to faulty operation and increased energy consumption.
We recommend carrying out the following procedure to correctly
adjust the overflow valve:
Close all of the heating circuits that may also be closed during
operation (depending on the type of heat pump usage) so that
the most unfavourable operating state - with respect to the water
flow rate - is achieved. This normally means the heating circuits
of the rooms on the south and west sides of the building. At least
one heating circuit must remain open (e.g. bathroom).
The overflow valve should be opened far enough to produce the
maximum temperature spread between the heating flow and re-
turn flow listed in the table below for the current heat source tem-
perature. The temperature spread should be measured as close
as possible to the heat pump. The heating element of mono en-
ergy systems should be disconnected.
Heat source
temperature
between heating flow and return
From
To
-5° C
0° C
1° C
5° C
6° C
9° C
10° C
14° C
15° C
20° C
21° C
25° C
Any faults occurring during operation are displayed on the heat
pump controller and can be corrected as described in the operat-
ing manual of the heat pump controller.
Max. temperature spread
flow
10 K
11 K
12 K
13 K
14 K
15 K