3.2 Commissioning

Checks to be done at first lighting, and after all maintenance operations that invol-
B
ved disconnection from the systems or work on safety devices or parts of the
boiler:
Before lighting the boiler
Open any on-off valves between the boiler and the systems.
Check the tightness of the gas system, proceeding with caution and using a soap and water solution to detect any
leaks in connections.
Check correct prefilling of the expansion tank (ref. sec. 4.4).
Fill the water system and make sure all air contained in the boiler and the system has been vented, by opening the
air vent valve on the boiler and any vent valves on the system.
Fill the condensate trap and check correct connection of the condensate elimination system.
Make sure there are no water leaks in the system, DHW circuits, connections or boiler.
Check correct connection of the electrical system and efficiency of the earthing system
Make sure the gas pressure value for heating is that required.
Make sure there are no flammable liquids or materials in the immediate vicinity of the boiler
IF THE ABOVE INSTRUCTIONS ARE NOT OBSERVED THERE MAY BE RISK
B
OF SUFFOCATION OR POISONING DUE TO GAS OR FUMES ESCAPING;
DANGER OF FIRE OR EXPLOSION. ALSO, THERE MAY BE A RISK OF ELEC-
TRIC SHOCK OR FLOODING THE ROOM.
Checks during operation
Turn the unit on as described in sec. 1.3.
Make sure the fuel circuit and water systems are tight.
Check the efficiency of the flue and air-fume ducts while the boiler is working.
Check the correct tightness and functionality of the condensate elimination system and trap.
Make sure the water is circulating properly between the boiler and the systems.
Make sure the gas valve modulates correctly in the heating and domestic hot water production phases.
Check proper boiler lighting by doing several tests, turning it on and off with the room thermostat or remote control.
Using a combustion analyser connected to the boiler fume outlet, check that the CO
boiler operating at max. and min. output, corresponds to that given in the technical data table for the corresponding
type of gas.
Make sure the fuel consumption indicated on the meter matches that given in the technical data table on sec. 4.4.
Check the correct programming of the parameters and carry out any necessary customization (compensation curve,
power, temperatures, etc.).

3.3 Maintenance

IMPORTANT
ALL MAINTENANCE WORK AND REPLACEMENTS MUST BE CARRIED OUT
B
BY SKILLED QUALIFIED PERSONNEL.
Before carrying out any operation inside the boiler, disconnect the power
and close the gas cock upstream. Otherwise there may be a danger of explo-
sion, electric shock, suffocation or poisoning.
Periodical check
To ensure lasting proper operation of the unit, it is necessary to have an annual inspection carried out by qualified per-
sonnel, providing for the following:
Heat exchanger check and cleaning with suitable products if dirty or clogged.
The exchanger can be cleaned only when its temperature is under 40°C.
Clean only with suitable products approved by the manufacturer, e.g.:
ALU CLEANGEL
BIO HALL LIQUID
Check and cleaning (if necessary) of burner (do not use chemical products or wire brushes).