9.2.1

Replacing the suction / pressure valve and metering cartridges

Tool:
Fig. 19: Maintenance: 3 ball valve (V3), 2.5 l/h
A
Connecting set (pos. 1-3)
1
Union nut
2
Clamping part
3
Tapered part
B
Suction, pressure valve (pos. 4-6)
4
O-ring, Ø 10 x 2.5
1.
Remove suction and pressure valve using an open spanner (SW 22)
2.
Mount all O-rings.
3.
Mount the metering cartridges (valve model V3)
4.
Screw in the new intake and pressure valves in the correct position
(tightening torque of 2-3 Nm).
n
Open-end spanner, SW 22 mm
45
5
Suction/pressure valve
6
O-ring, Ø 14 x 2.5
C
Metering cartridge V3 (pos. 7-9)
7
O-ring, Ø 7 x 1.5
8
Metering cartridges
9
O-ring, Ø 2.5 x 1.5