Unit Shutdown; Maintenance - Allmand NIGHT-LITE V Serie Manuel D'utilisation

Masquer les pouces Voir aussi pour NIGHT-LITE V Serie:
Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

Operating the Tower Lights
WARNING
Looking at illuminated light fixtures could result in serious
injury. Never look directly at illuminated light fixtures.
Turning the Lights On
The tower lights will automatically turn on after the engine is
started. (There is a 20-second delay built into the electrical
system.) However, the main light breaker or individual light
switches may be set to OFF.
• Turn on the main light breaker (A, Figure 24) (if set to
OFF).
• Turn on individual light switches (B, Figure 24) (1 - 4, if
set to OFF).
The breaker / switches may also be used if manual and
individual light control is desired.
Turning the Lights Off
Shut down the engine to turn the lights off. See Operating
the Engine . (The lights can also be turned off manually. See
Turning the Lights On .)
24
Auxiliary AC Outlets
Auxiliary AC outlets (A, B, C, Figure 25) are located on the
right rear of the machine. Each outlet is protected by a spring-
loaded cover.
Note: Outlets may differ according to model.
Power is supplied to the outlet(s) only when the engine is
running and the main circuit breaker (G, Figure 25) is in the
ON position. 
Note: The electrical system is designed with a 20-second
delay after the engine starts before the lights and auxiliary AC
outlet(s) will operate. 
Each outlet is protected by a dedicated circuit breaker (D, E,
F, Figure 25) found on the Light / AC Outlet Circuit Breaker
Control Panel.
Note: Circuit breakers differ according to outlets provided.
 If a breaker trips 
1. Disconnect the load from the outlet. 
2. Shut down the engine. 
3. Wait 10 minutes for the generator to cool down. 
4. Correct the load problem. 
5. Start the engine. 
6. Reset the breaker.
Note: Be sure to also check the GFCI breaker on the GFCI
outlet (if equipped), and reset if necessary. 
7. Reconnect the load. 
8. If the problem persists, see Troubleshooting. 
25

Unit Shutdown

Once lighting operations are complete at the work site,
perform unit shutdown: 
1. Shut down the engine. See  Operating the Engine . 
2. Wait 10 minutes for the lights to cool. 
3. Lower the light tower. See  Raising And Lowering the
Light Tower . 
4. Rotate the light tower to the transport position.
See  Adjusting the Lights . 
5. Adjust the light fixtures to the transport position.
See  Adjusting the Lights . 
6. Make sure the engine compartment cover is closed and
latched. 
7. Make sure the fuel door, radiator door and control panel
door are closed and secured. 
8. Retract the outriggers. See  Leveling and Stabilizing
the Light Tower Trailer . 
The unit is now ready for transport. See  Transporting . 
WARNING
Do not remove the wheel chocks from the front and back
of the wheels until the light tower trailer is connected to the
tow vehicle and ready to be transported. Doing so could
result in death or serious injury. 

Maintenance

Before performing any maintenance procedures,
read  Safety . 
23

Publicité

Table des Matières
loading

Table des Matières