OPERATION
FaST SYSTEM FREEZE PROTECTION (FaST Model)
Valve Coupling #1002856 and 15 cm (6.0 in) Hose
#63182 are required (Purchased separately).
1. Disconnect the FaST--PAK from the FaST system
and route the supply hose down to the scrub head
(Figure 59).
FIG. 59
2. Connect the valve coupling (purchased part) to the
supply hose and drain the remaining concentrate
into a small container (Figure 60). Squeeze the
supply hose several times if the concentrate does
not flow.
FIG. 60
3. Route the supply hose back up to the FaST--PAK
compartment. Connect the 15 cm (6.0 in) hose
(purchased part) to the valve coupling and pour
RV anti--freeze into the hose until full (Figure 61).
Squeeze the supply hose several times if the
anti--freeze does not flow.
22
Valve Coupling
Home
Find... Go To..
FIG. 61
4. Keep the hose upright to prevent the Anti--freeze
from spilling and lower the recovery tank.
5. Operate the FaST system until the foaming stops.
This step could take anywhere from 5--10 minutes.
6. Drain the solution tank.
7. Remove the valve coupling and connect the
supply hose to the storage plug (Figure 62).
FIG. 62
8. To drain the anti--freeze, repeat the draining
process above and reconnect the supply hose to
the FaST--PAK.

RECOMMENDED STOCK ITEMS

Refer to the Parts List section in this manual for
recommended stock items. Stock Items are clearly
identified with a bullet preceding the parts description.