068017-021 UL25, UL32 & UL40
O
I
UTRIGGER
1. Remove the outriggers from storage
locations on the sides of the mast.
2. Insert into the outrigger socket in the
base (Figure 1).
3. Push in until the locking pin engages
the hole in the end of the outrigger. Pull
outward on the outrigger to ensure
engagement.
4. Repeat the above steps for all other
outriggers. Make sure all four (4) lock-
ing pins are engaged.
5. Level the base, centering the bubble in
the orbit level on the base by adjusting the screwjacks (turn clockwise) at the end of each outrigger. DO
NOT release the tension (turn counterclockwise) on an outrigger to level the base.
6. All four (4) screwjack pads must be in solid contact with a firm surface and each outrigger indicator light
must be lit before the platform is elevated.
S
A F E T Y
D A N G E R
!
NEVER perform this test from the platform.
1. Properly install all four (4) outriggers and level the base.
2. Release the tension on one (1) outrigger by turning the screwjack counter clockwise until the indicator
light is no longer lit.
3. While standing on the ground, activate the control panel to elevate the platform. The platform should
not elevate.
4. Re-level the base.
5. Repeat steps 2, 3 and 4 until all four (4) outriggers have been tested.
D A N G E R
!
DO NOT use a machine that elevates when the tension has been released on an outrigger. The
machine must be repaired before using.
Page 6
NSTALLATION
I
T
N T E R L O C K
Bubble Level
Screwjack
E S T
!
!
Outrigger Installation
Figure 3: Installing Outriggers
Indicator Lights
Locking Pin
Operation Manual